‘Construction and engineering contracts often contain provisions specifying that, within a particular time, one party (traditionally the contractor) must notify the other (the employer and/or the contract administrator) of a claim or the likelihood that it might advance a claim. Sometimes these “time-bar” notice provisions are elevated beyond being merely an obligation, to the status of a condition precedent to being able to pursue a successful claim. If such provisions are enforceable, they can be severe: a failure to serve the required notice in the required timescale will be fatal, regardless of the merits of the underlying claim. A well-known example of such a provision is found in clause 20.1 of the 1999 FIDIC contracts.’
Full Story
Practical Law: Construction Blog, 20th February 2019
Source: constructionblog.practicallaw.com