Paying your fair share: when can an adjudicator decide more than the notified sum must be paid? – Hardwicke Chambers

Posted February 7th, 2017 in arbitration, construction industry, contracts, housing, news by sally

‘Judgment in the case of Kersfield Developments (Bridge Road) Ltd v Bray & Slaughter Ltd, handed down on 19 January 2017, is a new authority in the line of case law providing guidance on the provisions governing interim payments in Construction Contracts in the Housing Grants, Construction and Regeneration Act 1996, as amended (“the Act”).’

Full story

Hardwicke Chambers, 2nd February 2017

Source: www.hardwicke.co.uk