“Triple Point Technology Inc v PTT Public Company Limited [2021] UKSC 29” – Atkin Chambers

Posted November 4th, 2021 in contracts, damages, delay, negligence, news, Supreme Court by sally

‘The United Kingdom Supreme Court, allowing an appeal by PTT from the Court of Appeal, has clarified the relevant principles of English law relating to the construction of clauses providing for the payment of liquidated damages for delay. The Supreme Court has confirmed that, unless clear words in the contract provide otherwise, liquidated damages for delay will be an accrued right which is recoverable where the contract is terminated either under its terms or at law for repudiation.’

Full Story

Atkin Chambers, 6th October 2021