‘The Palladium is a mighty fine looking “superyacht”. It is an impressive 95 metres long and has all the features one would expect on such a luxury craft, including a helicopter landing pad and swimming pool. A Google search suggests that the yacht is worth circa $200 million, so one can see that a defect in the paint finish would be costly to rectify. It is this defect that ultimately led the parties to an arbitration, for which a five-week hearing was set.

The case ended up before the court because, during the arbitration, an issue arose as to whether the yacht builder’s without prejudice settlement offer had been accepted by the purchaser in correspondence. The purchaser contended that a binding settlement had been reached, which the builder denied.’

Full Story

Practical Law: Construction Blog, 29th May 2018

Source: constructionblog.practicallaw.com