Costs budgets- revisions and indemnity costs – 4 New Square

Posted June 26th, 2013 in amendments, budgets, costs, indemnities, news by sally

“On 14 June 2013 in Elvanite Full Circle Ltd v AMEC Earth & Environmental (UK) Ltd [2013] EWHC 1643 (TCC) Mr Justice Coulson handed down another important judgment on the application of the new costs management rules (in CPR r.3.15- r.3.18), albeit his decision relates to the Costs Management in Mercantile Courts and Technology and Construction Courts – Pilot Scheme (‘PD 51G’). In particular, Coulson J considered (i) the impact of an order for costs on the indemnity basis; (ii) what a party needs to do to seek approval of a revised costs budget; (iii) when a party should make an application for such approval; and (iv) what test the court applies on such an application. Coulson J’s findings are highlighted in bold below.”

Full story (PDF)

4 New Square, 25th June 2013

Source: www.4newsquare.com